Top Stories

Phase 1 Of The Clements Ferry Road Widening Project Underway

The first phase includes widening approximately 3.6 miles of Clements Ferry Road from I-526 to Jack Primus Road.
The first phase includes widening approximately 3.6 miles of Clements Ferry Road from I-526 to Jack Primus Road.

BERKELEY COUNTY, S.C.–The advance clearing has begun on Phase 1 of the Clements Ferry Road Widening Project.

The first phase includes widening approximately 3.6 miles of Clements Ferry Road from I-526 to Jack Primus Road.

It will also include two travel lanes in each direction plus center turn lane or raised planted median. A multi-purpose trail will be located on one side of the roadway.

Intersections within the project limits will be evaluated and improved if warranted.

Along with the clearing that’s underway, the silt fence installation has also begun.

Weather permitting, both of these actions are expected to be completed by July 1st.

The widening contract will be included in the July 12, 2016 SCDOT bid opening, with an anticipated construction starting in September 2016.
The widening contract will be included in the July 12, 2016 SCDOT bid opening, with an anticipated construction starting in September 2016.

The patching, milling, and initial paving operations is expected to being on July 10th and conclude on August 6th.

Weather permitting, additional moving items for the advance clearing is expected to be complete on September 30th.

Approximately 99% of right-of-way acquisition for Phase 1 of the project is complete. The critical path for this project is the utility relocation and the securing of utility agreements, county leaders stated.

The widening contract will be included in the July 12, 2016 SCDOT bid opening, with an anticipated construction starting in September 2016.

The entire project is expected to cost more than $29 million and be completed by 2021, according to SCDOT.
The entire project is expected to cost more than $29 million and be completed by 2021, according to SCDOT.

After Phase 1 is completed, Phase 2 will begin. It will consist of widening Clements Ferry Road for approximately 4.5 miles from Jack Primus Road to SC 41. The improvements involve widening the two-lane roadway to a four-lane curb and gutter section, with a raised planted median and multi-use path along one side of the roadway.

The entire project is expected to cost more than $29 million and be completed by 2021, according to SCDOT.

 

Comments are closed.